CPARS ratings: how they work and how to respond

CPARS is the governmentwide system where agencies record how a contractor performed. Under FAR 42.15, construction contracts of $900,000 or more must be rated at least annually and at completion, on a five-level scale. You get up to 14 calendar days after notice to comment, and disagreements go to a reviewer above the contracting officer.

Updated · By Nicolas Trendafilov, Vidikto publisher · 10 min read

Every federal contract above a set value leaves a written grade behind it, and future contracting officers read that grade when they choose who wins. This page explains which contracts get rated in CPARS, what the five rating levels mean, how long you have to answer, and how to write a response that a reviewer and a future evaluator will take seriously.

Not legal advice: this article explains the general rules; the solicitation of each contract governs.

Key terms

CPARS
The Contractor Performance Assessment Reporting System, named by FAR 42.1502 as the governmentwide tool where agencies enter past performance evaluations.
Past performance information
Ratings and narratives about how a contractor performed earlier contracts or orders, used by agencies when they select sources for new work (FAR 42.1501).
Interim and final evaluation
An interim evaluation is written while the work is still under way and is optional; the final evaluation is written when the work under the contract or order is completed (FAR 42.1502(a) and 42.1503(a)).

What CPARS records and why it matters

FAR 42.1501 defines past performance information as ratings and narratives about a contractor's actions under earlier contracts and orders. It lists what that record covers: meeting requirements and quality workmanship, forecasting and controlling costs, keeping to schedule, cooperative behavior and customer satisfaction, meeting small business subcontracting plans, reporting into required databases, integrity and business ethics, and a businesslike concern for the customer's interests.

The same section says CPARS is the official source for this information. When you bid on a negotiated contract later, the evaluation team pulls your CPARS evaluations and reads them next to the references you supply. Under FAR 15.305(a)(2), past performance is one indicator of your ability to perform, and the team considers how recent and how relevant each record is.

So a rating written about a small paving job in one district can come up years later when you bid on a building renovation with another agency. Treat every evaluation as a document that will be read by someone you have never met.

Which contracts get an evaluation

FAR 42.1502(a) requires evaluations at least annually and at the time the work under a contract or order is completed. The evaluation is generally written for the entity, division or unit that performed the work, and it goes into CPARS.

The dollar trigger depends on the kind of contract. Construction has its own threshold in paragraph (e), architect-engineer services have theirs in paragraph (f), and most other contracts and orders are rated when they exceed the simplified acquisition threshold. A contract terminated for default is rated whatever its value. Below the thresholds, an agency may still choose to write an evaluation.

Interim evaluations, written while work is still going on, are optional under FAR 42.1503(a). Many agencies write them on multi-year jobs, so a first-year rating can land long before the job is finished.

When FAR 42.1502 requires a CPARS evaluation
Kind of contractEvaluation requiredParagraph
ConstructionEach contract of $900,000 or more, and any construction contract terminated for default, whatever its value42.1502(e)
Architect-engineer servicesEach contract of $45,000 or more, and any such contract terminated for default, whatever its value42.1502(f)
Other contracts and ordersEach contract or order above the simplified acquisition threshold, including when a modification pushes it above42.1502(b)
Orders under Federal Supply Schedule or other agencies' contractsEach order above the simplified acquisition threshold42.1502(c)
Contracts awarded under subpart 8.7 (nonprofit agencies employing people who are blind or severely disabled)No evaluation42.1502(h)

The five rating levels

FAR 42.1503(b) lists the factors each evaluation must address at a minimum: technical quality, cost control (not used on firm-fixed-price or fixed-price with economic price adjustment contracts), schedule and timeliness, management or business relations, small business subcontracting, and other factors that apply. Most small construction contracts are firm-fixed-price, so cost control is usually left out.

Each factor gets a narrative and one of five ratings. The ratings must match the definitions in Table 42-1 of FAR 42.1503, or Table 42-2 for small business subcontracting when the contract contains the clause at FAR 52.219-9.

Read the definitions closely. Satisfactory means the contract requirements were met. It is not a poor grade, but a contractor who only ever gets Satisfactory has nothing that stands out when compared with a competitor rated Very Good. A rating above Satisfactory needs examples of how you exceeded requirements to the Government's benefit, and a rating below it needs examples of requirements you did not meet.

CPARS rating levels as defined in FAR 42.1503, Table 42-1
RatingWhat it means in Table 42-1
ExceptionalPerformance meets contractual requirements and exceeds many to the Government's benefit.
Very GoodPerformance meets contractual requirements and exceeds some to the Government's benefit.
SatisfactoryPerformance meets contractual requirements.
MarginalPerformance does not meet some contractual requirements.
UnsatisfactoryPerformance does not meet most contractual requirements and recovery is not likely in a timely manner.

The 14-day comment window

When an evaluation is ready, CPARS sends you an automatic notice. FAR 42.1503(d) gives you up to 14 calendar days from that notification to submit comments, rebuttal statements or additional information. Calendar days include weekends and holidays, so a notice that arrives on a Friday before a long weekend still runs on the same clock.

The agency does not wait for you. Under FAR 42.1503(f), the evaluation, including any information you submitted, becomes available to source selection officials no later than 14 days after you were notified, flagged if an agency review is still pending. Comments you send after that are added to CPARS later, along with any review that follows.

Make sure the notices reach a person who reads them. If the email address CPARS holds for your company belongs to someone who left last year, the window can close without anyone noticing.

Writing a response that counts

Your response stays attached to the evaluation. A future evaluator who reads a Marginal rating will also read what you wrote, so write for that person as much as for the reviewing official.

Stick to facts that can be checked. If the narrative says the job finished late, give the dates of the change orders that extended the work, the date of the government's late approval of a submittal, or the weather days granted in writing. Quote contract modifications by number. If the narrative says workmanship was poor, describe what was corrected, when, and whether the government accepted the corrected work.

Keep the tone flat. Arguments about personalities, or claims that the inspector disliked your crew, weaken the response. Agree with what is accurate and dispute only what is wrong. If the rating itself is consistent with the narrative but the narrative leaves out context, add the context and ask for the narrative to be completed.

If you still disagree after the agency replies, ask for review. FAR 42.1503(d) requires agencies to provide review at a level above the contracting officer to settle disagreements. The final conclusion on the evaluation is the contracting agency's decision.

How long a rating follows you

FAR 42.1503(g) limits how far back source selection officials may look. They use past performance information within three years of the completion of performance of the evaluated contract or order, and within six years for construction and architect-engineer contracts.

For a construction firm, that means a rating written at the end of a job can weigh on bids for six years after the work was completed. A strong rating helps for just as long, which is one more reason to ask the contracting officer, before the final evaluation is drafted, what went well on the job.

While the information can be used for source selection, FAR 42.1503(d) says the completed evaluation may be released only to Government personnel and to the contractor evaluated. It is not posted for the public or for your competitors.

If you have no CPARS record yet

A first federal contract raises the opposite question: what happens when there is nothing to read. FAR 15.305(a)(2) says an offeror without a record of relevant past performance, or for whom information is not available, may not be evaluated favorably or unfavorably on past performance.

The same paragraph requires the solicitation to let offerors identify past or current contracts, including federal, state, local and private work. A municipal job or a large private renovation can count, so list it with contact names who will answer the phone.

Responding to a CPARS evaluation
Responding to a CPARS evaluation : Note the date ; Read factor by factor ; Gather the file

Responding to a CPARS evaluation

  1. Note the date. Write down the date of the CPARS notification and count 14 calendar days from it.
  2. Read factor by factor. Compare each rating with its narrative and with the Table 42-1 definition of that rating.
  3. Gather the file. Pull the modifications, daily logs, submittal approvals and emails that confirm or contradict the narrative.
  4. Write the response. Agree with what is accurate, dispute only what is wrong, and cite each document by number and date.
  5. Submit in CPARS. Enter your comments in CPARS before the 14 days run out, even if the rating is good.
  6. Ask for review. If you still disagree after the reply, request review at the level above the contracting officer.

Frequently asked questions

Can a CPARS rating be changed after I comment?

Yes, the agency can revise the evaluation after reading your comments, and a reviewer above the contracting officer settles disagreements. FAR 42.1503(d) leaves the final decision to the contracting agency.

What happens if I miss the 14-day window?

The evaluation becomes available to source selection officials no later than 14 days after notification, with or without your comments. Under FAR 42.1503(f), comments received later are added to CPARS afterward, so a late response is still worth sending.

Is a Satisfactory rating bad?

No. Table 42-1 defines Satisfactory as performance that meets contractual requirements. It simply gives a future evaluator less to set you apart than Very Good or Exceptional.

Should I comment on a good rating?

Comments are optional. A short note that thanks the agency and adds a fact the narrative left out, such as an early completion date, costs little and stays attached to the record.

Can competitors see my CPARS evaluations?

No. FAR 42.1503(d) limits release of a completed evaluation to Government personnel and the contractor evaluated while it can be used for source selection.

Sources and republications