When price alone cannot decide, agencies buy by negotiation under FAR Part 15. This page explains what an RFP must tell you, how tradeoff and LPTA selections differ, what the competitive range and discussions mean for your proposal, and how to request a debriefing in time to learn from a loss.
Not legal advice: this article explains the general rules; the solicitation of each contract governs.
Key terms
- Tradeoff process
- A source selection in which the agency may award to an offeror that is not the lowest priced or the highest rated, when the benefits justify the price. FAR 15.101-1 governs it.
- Lowest price technically acceptable (LPTA)
- A source selection in which proposals are rated only acceptable or unacceptable on non-price factors, and the acceptable proposal with the lowest evaluated price wins. FAR 15.101-2 governs it.
- Competitive range
- The group of most highly rated proposals the contracting officer keeps for discussions under FAR 15.306(c). Offerors outside it are notified in writing.
- Debriefing
- A meeting or letter in which the agency explains its evaluation of your proposal and the basis of its decision, given on written request under FAR 15.505 or 15.506.
What the RFP must tell you
A negotiated acquisition starts with a request for proposals. FAR 15.203(a) sets the minimum content of an RFP in a competitive acquisition: the Government's requirement, the anticipated terms and conditions, the information you must put in your proposal, and the evaluation factors and significant subfactors with their relative importance.
FAR 15.203(c) allows agencies to issue RFPs and receive proposals electronically, and the RFP must state the methods offerors may use. Read that instruction as closely as the deadline: a proposal sent by an unauthorized method can be lost.
Start with the factors. They tell you what the agency will score, and their order tells you where to spend your writing time. In many RFPs they appear in Section M, with the proposal instructions in Section L, but the uniform contract format is not always used. Find the factors wherever your RFP puts them.
Tradeoff: best value beyond the lowest price
FAR 15.101-1 describes the tradeoff process. It fits when it may be in the Government's interest to award to an offeror other than the lowest priced or the highest technically rated. The RFP must clearly state every evaluation factor and significant subfactor that will affect award, and their relative importance.
The RFP must also say how the non-price factors, combined, compare to price: significantly more important than, approximately equal to, or significantly less important than cost or price. That one sentence tells you whether a stronger technical approach can carry a higher price.
When the agency pays more for a better proposal, the perceived benefits must merit the extra cost, and the rationale must be documented in the file. That record is what a debriefing draws on later.
LPTA: pass or fail, then price
FAR 15.101-2 describes the lowest price technically acceptable process. It fits when best value is expected from choosing the technically acceptable proposal with the lowest evaluated price. The RFP states the factors and significant subfactors that set acceptability, and award goes to the lowest evaluated price among proposals that meet them.
Tradeoffs are not permitted. Proposals are evaluated for acceptability but not ranked on non-price factors. Past performance need not be a factor if the contracting officer documents why; when it is used and a small business is rated unacceptable on it, the matter is referred to the SBA for a Certificate of Competency.
The same section limits LPTA outside DoD: it is to be used when requirements can be clearly described and the agency sees little value in exceeding the minimum, and avoided to the maximum extent practicable for knowledge based services such as information technology and cybersecurity.
| Point | Tradeoff (FAR 15.101-1) | LPTA (FAR 15.101-2) |
|---|---|---|
| Who wins | The offeror whose proposal is the best value under the stated factors, not necessarily the lowest price | The technically acceptable proposal with the lowest evaluated price |
| Non-price factors | Rated and compared; relative importance stated in the RFP | Rated acceptable or unacceptable only; not ranked |
| Price against quality | RFP states whether non-price factors combined are more important than, equal to, or less important than price | Tradeoffs are not permitted |
| Past performance | Evaluated as the RFP states | Need not be a factor if documented; a small business found unacceptable is referred to the SBA |
| What to write | Strengths that justify your price on each factor | A clean, compliant proposal at the sharpest price |
The proposal deadline
FAR 15.208 puts the delivery risk on you. The proposal must reach the designated office by the time the solicitation sets, or by 4:30 p.m. local time on the due date if no time is set. A late proposal is considered only if it arrives before award, does not unduly delay the acquisition, and either reached the Government's electronic point of entry by 5:00 p.m. one working day before the due date, was shown to be under Government control at the installation before the deadline, or was the only proposal received.
That third case does not exist in sealed bidding. It is a narrow door; plan as if the deadline were absolute and upload a day early.
Award without discussions, or a competitive range
After proposals arrive, the agency has two paths under FAR 15.306. If the RFP said it intends to award without discussions, it may do so. Only clarifications then take place: limited exchanges that may let you clarify certain aspects of your proposal or fix minor or clerical errors. This is why your first proposal must be complete.
Otherwise, the contracting officer sets a competitive range of the most highly rated proposals. If the RFP said so, the range may be further limited for efficiency. Offerors left out receive written notice under FAR 15.503(a), which states the basis for the decision and that a revised proposal will not be considered, and they may request a debriefing.
Before the range is set, FAR 15.306(b) allows only limited communications, with offerors whose past performance decides whether they make the range or whose inclusion is uncertain. These communications may not be used to cure deficiencies or revise a proposal.
Discussions: what the agency must raise
Discussions are held with every offeror in the competitive range and tailored to each proposal. Their purpose under FAR 15.306(d) is to maximize the Government's ability to obtain best value. At a minimum, the contracting officer must raise deficiencies, significant weaknesses, and adverse past performance information you have not yet had a chance to answer.
FAR 15.306(e) sets limits. Government staff may not favor one offeror over another, reveal another offeror's technical solution, or reveal another offeror's price without permission. They may tell you that your price is considered too high or too low, and they may not reveal the names of people who gave past performance references.
Treat a discussion notice as a scoring sheet. Answer every point in writing, revise the proposal where asked, and check that your final proposal revision fixes each deficiency named.
Debriefings: ask within 3 days
A debriefing is your best feedback after a loss, and it depends on a short deadline. If you are excluded before award, FAR 15.505 lets you ask for a preaward debriefing by written request to the contracting officer within 3 days after you receive the notice of exclusion. You may ask to delay it until after award. An offeror who misses the 3 day window is not entitled to either a preaward or a postaward debriefing.
After award, FAR 15.503(b) requires a notice to unsuccessful offerors within 3 days after the award date, with the number of proposals received, the awardee's name and address, and the award prices. Under FAR 15.506(a), you then have 3 days after receiving notice of award to request a debriefing in writing, and it should occur within 5 days after the agency receives your request, to the maximum extent practicable.
A postaward debriefing gives at least the significant weaknesses or deficiencies in your proposal, the overall evaluated price and technical rating of the awardee and of your proposal, your past performance information, the overall ranking of all offerors if one was made, a summary of the award rationale, and answers on whether procedures were followed. It does not give point by point comparisons with other proposals or protected commercial information.
| Event | Deadline | Rule |
|---|---|---|
| Request a preaward debriefing after exclusion | Written request within 3 days after receiving the exclusion notice | FAR 15.505 |
| Notice to unsuccessful offerors after award | Within 3 days after the date of award | FAR 15.503(b)(1) |
| Request a postaward debriefing | Written request within 3 days after receiving notice of award | FAR 15.506(a) |
| Agency holds the postaward debriefing | Within 5 days after receiving the request, to the maximum extent practicable | FAR 15.506(a) |
Frequently asked questions
Can the agency award to a higher price than mine?
Yes, under a tradeoff process. FAR 15.101-1 allows award to an offeror other than the lowest priced when the benefits of the higher priced proposal merit the extra cost, and the rationale must be documented. Under LPTA, tradeoffs are not permitted.
Will the agency always hold discussions?
No. Under FAR 15.306, it may award without discussions if the RFP stated that intent. Then only clarifications take place, so your initial proposal should be your best one.
What if I miss the 3 day window for a debriefing?
Under FAR 15.506(a), an untimely request may be accommodated, but this does not extend protest deadlines. An offeror excluded before award who did not ask in time is not entitled to a debriefing.
Will a debriefing show me my competitors' proposals?
No. FAR 15.506(e) bars point by point comparisons with other proposals and protected information such as trade secrets, cost breakdowns and profit. You do receive the awardee's overall evaluated price and technical rating.
Sources and republications
The dates below concern links. They do not certify a full substantive review; claims and applicable versions still need review. Article review record.
- FAR 15.203, Requests for proposals, link checked on
- FAR 15.101-1, Tradeoff process, link checked on
- FAR 15.101-2, Lowest price technically acceptable source selection process, link checked on
- FAR 15.208, Submission, modification, revision, and withdrawal of proposals, link checked on
- FAR 15.306, Exchanges with offerors after receipt of proposals, link checked on
- FAR 15.503, Notifications to unsuccessful offerors, link checked on
- FAR 15.505, Preaward debriefing of offerors, link checked on
- FAR 15.506, Postaward debriefing of offerors, link checked on