Past performance evaluation in federal proposals

In a negotiated federal acquisition above the simplified acquisition threshold, past performance is normally an evaluation factor under FAR 15.304. Evaluators judge how relevant and recent your earlier contracts are, using your references and CPARS records. A firm with no relevant record cannot be rated favorably or unfavorably on past performance under FAR 15.305(a)(2)(iv).

Updated · By Nicolas Trendafilov, Vidikto publisher · 9 min read

Past performance is the factor that worries small firms most, because it seems to reward those who already have federal work. This page sets out when the FAR requires it, how relevance and recency are judged, what the neutral rating means for a firm with no record, and how to present the experience you do have.

Not legal advice: this article explains the general rules; the solicitation of each contract governs.

Key terms

Past performance
Your record on earlier contracts, as it is used to predict how well you will perform the new one. It is scored as one of the evaluation factors in Section M.
Relevance
How close an earlier contract is to the new requirement in scope, size and complexity. The solicitation says how it will be judged.
Recency
How recently the earlier work was performed. The FAR calls it currency, and the solicitation often sets a period to look back on.
Neutral rating
The result for an offeror with no relevant past performance record: it may not be evaluated favorably or unfavorably on that factor.

When past performance is evaluated

FAR 15.304(c)(3) requires past performance to be evaluated in all source selections for negotiated competitive acquisitions expected to exceed the simplified acquisition threshold. The contracting officer may leave it out only by documenting why it is not an appropriate evaluation factor for that acquisition.

It is one way the FAR makes agencies look beyond price. FAR 15.304(c)(2) requires the quality of the product or service to be addressed in every source selection, and lists past performance among the non-cost factors that can do so, next to technical excellence and management capability.

Smaller and simpler buys work differently. Below the simplified acquisition threshold, or under sealed bidding, the solicitation may still mention past performance, but the rules of FAR 15.304 and 15.305 described here apply to negotiated proposals under Part 15. Read the basis for award in your own solicitation.

How evaluators judge relevance and recency

FAR 15.305(a)(2)(i) tells the agency to consider the currency and relevance of the information, its source, the context of the data, and general trends in the contractor's performance. A large contract done well ten years ago may weigh less than a smaller, similar job finished last year.

The solicitation must explain the approach. Under FAR 15.305(a)(2)(ii), it describes how past performance will be evaluated, including for offerors with no relevant record, and it gives offerors a chance to identify past or current contracts, federal, state and local government or private, for efforts similar to the requirement. It must also let you describe any problems on those contracts and the corrective actions you took.

Relevance is usually defined in the solicitation by scope, size and complexity. Section L often caps the number of references, and Section M says how relevance and quality combine into a rating. Follow those definitions exactly when you pick which jobs to cite.

No record: the neutral rating

A new firm, or a firm new to federal work, has a protection written into the FAR. Under FAR 15.305(a)(2)(iv), an offeror without a record of relevant past performance, or for which past performance information is not available, may not be evaluated favorably or unfavorably on past performance.

In practice the rating is called neutral. It keeps you in the competition, but it does not earn the credit a strong record would. When past performance is heavily weighted in Section M, a neutral rating can still leave you behind a competitor with excellent references, so the other factors and your price have to carry more of the weight.

A neutral rating is not automatic for a firm that does have experience. If you have similar private or state and local work, cite it: the solicitation must let you identify those contracts, and relevant non-federal work can count.

Whose experience can count

Your firm's record is not the only one evaluators may look at. FAR 15.305(a)(2)(iii) says the evaluation should take into account past performance information on predecessor companies, key personnel who have relevant experience, and subcontractors that will perform major or critical aspects of the requirement, when that information is relevant.

That gives a small firm three openings. A foreman or project manager who ran similar federal jobs for a previous employer brings that experience with them as key personnel. A firm that took over another business may cite the predecessor's record. A subcontractor who will perform a critical part of the work can lend its record for that part.

Each opening has a cost. Key personnel must be named in the proposal and should stay on the job. A subcontractor's record only counts for the work it will really perform. Check Section L for the form these references must take.

What the FAR says on each past performance question
QuestionRuleWhat it says
Must it be evaluated?FAR 15.304(c)(3)Yes, in negotiated competitive acquisitions above the simplified acquisition threshold, unless documented as not appropriate.
How is it judged?FAR 15.305(a)(2)(i)Currency, relevance, source, context and general trends.
Which contracts can I cite?FAR 15.305(a)(2)(ii)Past or current federal, state, local government and private contracts for similar efforts.
Whose record counts?FAR 15.305(a)(2)(iii)Predecessor companies, key personnel with relevant experience, and subcontractors on major or critical aspects.
No record?FAR 15.305(a)(2)(iv)Not evaluated favorably or unfavorably on past performance.
How far back in CPARS?FAR 42.1503(g)Within three years of completion, six for construction and architect-engineer contracts.

CPARS: the record that follows you

Once you win federal work, your record builds itself. FAR 42.1502(a) requires past performance evaluations at least annually and when the work is completed, entered in CPARS. For construction, FAR 42.1502(e) requires an evaluation for each contract of $900,000 or more, and for any construction contract terminated for default, whatever its value; below that amount evaluations are optional.

Under FAR 42.1503(d), you receive a notification when an evaluation is ready and have up to 14 calendar days to submit comments, rebuttals or additional information. Disagreements are reviewed at a level above the contracting officer. Use those days: a factual rebuttal, attached to the record, is read by the next evaluator too.

Source selection officials then use the CPARS information that is within three years of the completion of the evaluated contract, or six years for construction and architect-engineer contracts, under FAR 42.1503(g). A good construction rating keeps working for you long after the job.

Adverse information and your chance to answer

The FAR gives you a voice when the record is negative. Under FAR 15.306(a)(2), when the Government plans to award without discussions, offerors may be given the chance to clarify the relevance of their past performance and adverse past performance information to which they have not previously had an opportunity to respond.

If the agency sets a competitive range and opens discussions, FAR 15.306(d)(3) requires the contracting officer, at a minimum, to raise adverse past performance information to which the offeror has not yet had an opportunity to respond. Prepare a short, factual explanation of any troubled job before you submit, with the corrective actions you took.

What a small firm can do now

A fictitious example: a four-person electrical firm has ten years of commercial and school district work but no federal contract. It cites three school district jobs close in size to the federal project, names its master electrician as key personnel with his earlier federal job for another employer, and lists the mechanical subcontractor's federal record for the HVAC portion.

Start the groundwork early, before a solicitation is open:

  • Keep a file per finished job: owner, contact, value, dates, scope and any problem solved.
  • Ask satisfied owners in advance whether they will answer a federal questionnaire.
  • Take small federal subcontracts or simplified acquisitions to start a CPARS record.
  • Answer every CPARS notification within the 14 days.

Frequently asked questions

Does no past performance mean I will lose?

No. FAR 15.305(a)(2)(iv) says an offeror without a relevant record may not be evaluated favorably or unfavorably on past performance. The other factors and your price then decide, in the weights stated in Section M.

Can private or state and local work count?

Yes. FAR 15.305(a)(2)(ii) asks the solicitation to let offerors identify federal, state and local government and private contracts for similar efforts. The solicitation defines what counts as similar.

How long does a CPARS rating stay in use?

Under FAR 42.1503(g), agencies use CPARS information within three years of completion, and six years for construction and architect-engineer contracts.

Can I use my project manager's experience from another company?

FAR 15.305(a)(2)(iii) says the evaluation should consider key personnel who have relevant experience. Name that person in the proposal as Section L asks, and plan for them to work on the job.

Sources and republications

The dates below concern links. They do not certify a full substantive review; claims and applicable versions still need review. Article review record.