On federal construction, bonds decide whether your bid stays in the running and whether you can sign the contract. This page sets out when the Miller Act requires performance and payment bonds, what a bid guarantee is and how much it must be, which sureties the Government accepts, and what changes on smaller jobs.
Not legal advice: this article explains the general rules; the solicitation of each contract governs.
Key terms
- Bid guarantee
- A promise, backed by a bond, a check or a letter of credit, that you will sign the contract and furnish the required bonds if your bid is selected.
- Penal amount
- The maximum sum the surety can be made to pay under a bond. For performance and payment bonds it is generally the full contract price.
- Surety
- The company that issues the bond and answers for your obligations if you fail to meet them. On federal work it must appear on Treasury Circular 570.
- Miller Act
- The former name of the federal Bonds statute, now at 40 U.S.C. 3131 to 3134, which requires performance and payment bonds on federal construction.
Three bonds, three jobs
Federal construction uses three kinds of bonds, each on its own Standard Form listed in FAR 28.106-1.
- The bid bond, SF 24: it backs your promise that, if selected, you will sign the contract and furnish the other bonds.
- The performance bond, SF 25: it protects the Government if you do not finish the work.
- The payment bond, SF 25A: it protects the people who supply labor and material to the job, such as your subcontractors and suppliers.
| Bond | Form | Who it protects | Usual amount |
|---|---|---|---|
| Bid bond | SF 24 | The Government, against a selected bidder who will not sign or furnish bonds | At least 20 percent of the bid price, not more than $3 million (FAR 28.101-2(b)) |
| Performance bond | SF 25 | The Government, if the work is not finished | Generally 100 percent of the original price plus increases (FAR 28.102-2) |
| Payment bond | SF 25A | Subcontractors and suppliers of labor and material | 100 percent of the original price plus increases, never less than the performance bond (FAR 28.102-2) |
When the Miller Act requires performance and payment bonds
The Miller Act now sits in title 40 of the United States Code, chapter 31, subchapter III, which FAR 28.102-1 calls the Bonds statute, formerly known as the Miller Act. Its first section, 40 U.S.C. 3131(b), requires a performance bond and a payment bond before any contract of more than $100,000 is awarded for the construction, alteration or repair of a public building or public work of the Federal Government.
The FAR applies a higher figure. FAR 28.102-1(a), read on acquisition.gov on October 27, 2026, says the Bonds statute requires performance and payment bonds for any construction contract exceeding $150,000. The contracting officer works from the FAR, so the figure in your solicitation is the one to follow.
The waiver in FAR 28.102-1(a) is narrow: the work performed in a foreign country, or as otherwise authorized by the Bonds statute or other law.
The solicitation tells you. On SF 1442, Block 12a says whether performance and payment bonds are required and Block 12b gives the number of calendar days after award to furnish them.
How large the bonds must be
Under FAR 28.102-2, the performance bond is generally 100 percent of the original contract price, plus 100 percent of any price increase, unless the contracting officer decides a lesser amount is adequate.
The payment bond is also 100 percent of the original contract price plus increases. A smaller payment bond needs a written determination by the contracting officer, with findings, that the full amount is impractical, and it can never be less than the performance bond. 40 U.S.C. 3131(b)(2) sets the same floor.
Price that into your bid. Ask your surety for the premium on a bond equal to your full bid amount, not just on the bid bond.
The bid guarantee: when it is asked and how much
A bid guarantee follows the bonds. FAR 28.101-1(a) says it shall be required whenever a performance bond or a performance and payment bond is required, and a contracting officer shall not require one otherwise. The chief of the contracting office can waive it for a specific acquisition, for example an emergency or a sole-source award.
On construction, FAR 28.101-1(b) accepts only separate bid guarantees. You furnish a guarantee for this bid alone.
The amount comes from FAR 28.101-2(b): at least 20 percent of the bid price, but not more than $3 million. The solicitation states it, often as a percentage, sometimes with a dollar cap.
Provision 52.228-1 goes into the solicitation. It lists what you may furnish: a bid bond with good and sufficient surety, a postal money order, a certified or cashier's check, an irrevocable letter of credit, or certain bonds or notes of the United States. A bid bond is the usual choice because it does not tie up your cash.
A missing or defective guarantee
In sealed bidding, the rule is strict. FAR 28.101-4(a) says noncompliance with a solicitation requirement for a bid guarantee requires rejection of the bid, and FAR 14.404-2(j) repeats it.
FAR 28.101-4(c) lists the cases where the noncompliance shall be waived, unless the contracting officer determines in writing that accepting the bid would be detrimental to the Government's interest:
- Only one offer is received.
- The guarantee is less than required but at least equal to the difference between your price and the next higher acceptable offer.
- The guarantee arrives late and the late receipt is waived under FAR 14.304.
- The bid bond was not signed by the offeror.
- The bid bond is dated wrong or not dated at all.
- The bid bond does not list the United States as obligee.
Which sureties the Government accepts
A bond is only as good as its surety. FAR 28.202 says corporate sureties on bonds for contracts performed in the United States must appear on the Department of the Treasury's Listing of Approved Sureties, Department Circular 570.
The list also gives each surety an underwriting limit. The penal amount of the bond should not exceed that limit; above it, the excess must be coinsured or reinsured within the limits of the other companies.
Before you pay a premium, check the surety's name on the Treasury listing and compare its limit with your bond amount. The listing is published by the Bureau of the Fiscal Service, as FAR 28.202 explains.
Jobs between $35,000 and $150,000
Below the Miller Act line, subcontractors and suppliers still get some protection. FAR 28.102-1(b)(1) says that for construction contracts greater than $35,000 but not greater than $150,000, the contracting officer selects two or more payment protections, with particular consideration of an irrevocable letter of credit.
The options listed are a payment bond, an irrevocable letter of credit, a tripartite escrow agreement, certificates of deposit, or a deposit of the securities listed in FAR 28.204-1 and 28.204-2. You then submit one of the protections the contracting officer selected.
The Miller Act also explains why the payment bond matters to the people you hire. Under 40 U.S.C. 3133, a supplier or subcontractor unpaid 90 days after its last labor or material may sue on the payment bond, and a second-tier claimant must first give the prime contractor written notice within 90 days. The suit must be filed within one year after the last labor or material.
What to do before the due date
Bonding takes time, and the surety will want your financial statements and work history. Start as soon as you decide to bid.
Getting your bonds ready, step by step
- Read the solicitation. Read SF 1442 Blocks 12a, 12b and 13b, and the bid guarantee provision in the solicitation.
- Get the bid bond. Get the bid bond on SF 24, current revision 10/2023 in the GSA forms library, for the amount the solicitation states.
- Check the bond. Check that the bond is signed, dated and names the United States as obligee.
- Check the surety. Confirm your surety is on the Treasury listing with enough underwriting limit for the bond amount.
- Line up the contract bonds. Get a written commitment for the performance and payment bonds you will need within the days set in Block 12b.
Frequently asked questions
Is the Miller Act threshold $100,000 or $150,000?
The statute at 40 U.S.C. 3131(b) still reads more than $100,000, while FAR 28.102-1(a) applies $150,000. Contracting officers follow the FAR, and the solicitation states what it requires.
Can I use a cashier's check instead of a bid bond?
Yes, provision 52.228-1 accepts a certified or cashier's check, a postal money order, an irrevocable letter of credit and certain United States bonds or notes. Guarantees other than bid bonds are returned to unsuccessful bidders soon after bid opening.
Does a bid on a $60,000 job need a bid bond?
Under FAR 28.101-1(a), a bid guarantee is required only when a performance bond or a performance and payment bond is required. Read the solicitation: Block 13b of SF 1442 says whether one is required.
What happens if I am selected but cannot get the bonds?
Provision 52.228-1(d) allows termination for default if you do not execute the contract and furnish the bonds within 10 days after receiving the forms, and your bid guarantee can be applied to the extra cost of buying the work elsewhere.
Sources and republications
The dates below concern links. They do not certify a full substantive review; claims and applicable versions still need review. Article review record.
- 40 U.S.C. 3131, Bonds of contractors of public buildings or works (Cornell republication), link checked on
- 40 U.S.C. 3133, Rights of persons furnishing labor or material (Cornell republication), link checked on
- FAR 28.102-1, General (performance and payment bonds for construction contracts), link checked on
- FAR 28.102-2, Amount required, link checked on
- FAR 28.101-1, Policy on use (bid guarantees), link checked on
- FAR 28.101-2, Solicitation provision or contract clause (bid guarantee amount), link checked on
- FAR 28.101-4, Noncompliance with bid guarantee requirements, link checked on
- FAR 52.228-1, Bid Guarantee, link checked on
- FAR 28.106-1, Bonds and miscellaneous (forms), link checked on
- FAR 28.202, Acceptability of corporate sureties, link checked on
- FAR 14.404-2, Rejection of individual bids, link checked on
- GSA Forms Library, SF 24, Bid Bond, link checked on