IFB, RFP or RFQ: which federal solicitation you have

An IFB is sealed bidding under FAR Part 14: bids are opened in public and the low responsive, responsible bidder wins on price. An RFP is a negotiated acquisition under FAR Part 15, scored on stated factors with possible discussions. An RFQ asks for quotations under the simplified procedures of FAR Part 13, and a quotation is not an offer.

Updated · By Nicolas Trendafilov, Vidikto publisher · 9 min read

Federal construction work comes as an invitation for bids, a request for proposals or a request for quotations, and each one follows a different part of the FAR. This page explains how each is evaluated, what it changes for the way you price and submit, and where to look in the package to know which one you hold.

Not legal advice: this article explains the general rules; the solicitation of each contract governs.

Key terms

Invitation for bids (IFB)
The solicitation used in sealed bidding under FAR Part 14. Bids are opened publicly and evaluated on price and price-related factors only, without discussions.
Request for proposals (RFP)
The solicitation used in negotiated acquisitions under FAR Part 15. It states the evaluation factors and their relative importance, and award goes to the best value.
Request for quotations (RFQ)
The usual solicitation of simplified acquisition under FAR Part 13. The quotation you send is not an offer; the Government's order is.

Three methods, three parts of the FAR

The invitation for bids, or IFB, is sealed bidding under FAR Part 14. The request for proposals, or RFP, is a negotiated acquisition under FAR Part 15. The request for quotations, or RFQ, is the usual tool of simplified acquisition under FAR Part 13.

The method is chosen by the contracting officer, not by you. But it decides how your price is judged, whether anyone talks to you after submission, and how strict the deadline is.

IFB, RFP and RFQ compared
PointIFB (FAR Part 14)RFP (FAR Part 15)RFQ (FAR Part 13)
Basis of awardPrice and price-related factors only (FAR 14.101)Stated factors and their relative importance; tradeoff possible (FAR 15.203, 15.101-1)The basis stated in the solicitation, price alone or price and other factors (FAR 13.106-2)
OpeningPublic bid opening, bids read aloud if practical (FAR 14.402-1)No public openingNo public opening
Talks after submissionNone; bids evaluated without discussionsPossible discussions with offerors in the competitive range (FAR 15.306)Not required; formal discussions and scoring are not needed
Legal effect of your responseA bid the Government can acceptAn offer the Government can acceptA quotation that is not an offer (FAR 13.004)
Late submissionsTwo narrow exceptions (FAR 14.304)Same two exceptions plus the only proposal received (FAR 15.208)Follow the deadline and delivery instructions in the RFQ

Sealed bidding (IFB): price decides

FAR 6.401(a) tells contracting officers to solicit sealed bids when four conditions hold: time permits, award will be made on price and price-related factors, discussions are not necessary, and more than one bid is reasonably expected.

For construction, FAR 36.103(a) makes this binding: the contracting officer shall use sealed bid procedures for a construction contract if the conditions in 6.401(a) apply, except for work outside the United States and its outlying areas.

FAR 14.101 describes the steps. The invitation describes the requirement clearly, accurately and completely. Bids are submitted sealed, opened in public, and evaluated without discussions. Award goes to the responsible bidder whose bid meets the invitation and is most advantageous to the Government, considering only price and the price-related factors in the invitation.

For you, this means no technical narrative to write and no chance to improve your bid after opening. The low responsive, responsible bidder gets the job. Your work is in the takeoff and in filling the forms exactly.

Public bid opening

Under FAR 14.402-1, the bid opening officer announces when the set time has arrived, then personally and publicly opens all bids received before that time, reads them aloud if practical, and has them recorded.

Interested persons may examine the bids, as long as it does not interfere unduly with the conduct of Government business. So after an IFB, you can see who bid and at what price. That is useful for your next estimate.

Negotiated proposals (RFP): factors and tradeoffs

When sealed bidding does not fit, FAR 6.401(b) allows competitive proposals. FAR 15.203(a) says an RFP for a competitive acquisition must, at a minimum, describe the Government's requirement, the anticipated terms and conditions, the information your proposal must include, and the evaluation factors and significant subfactors with their relative importance.

That last item is the one to read first. Under a tradeoff process, FAR 15.101-1 allows award to an offeror other than the lowest priced or the highest technically rated. The solicitation must say whether all non-price factors combined are significantly more important than, approximately equal to, or significantly less important than price.

Exchanges can happen after submission. Under FAR 15.306, the Government may award without discussions if the solicitation says it intends to. Otherwise, it sets a competitive range of the most highly rated proposals and holds discussions with each offeror in it, raising at least deficiencies, significant weaknesses and adverse past performance information you have not had a chance to answer.

So write your first proposal as if it were your last. Past performance, schedule and approach count, and the solicitation tells you how much.

Requests for quotations (RFQ): a quote is not an offer

Simplified acquisition covers purchases up to the simplified acquisition threshold. The FAR 2.101 definition, read on acquisition.gov on October 27, 2026, sets that threshold at $350,000 for most acquisitions, with higher figures for contingency and emergency cases. FAR 13.003(a) asks agencies to use simplified procedures to the maximum extent practicable at or below it.

The legal effect is different. FAR 13.004(a) says a quotation is not an offer and cannot be accepted by the Government to form a binding contract. The order the Government issues in response to your quote is the offer, and a contract exists only when you accept it, in writing if asked, or by performing the work.

The evaluation is lighter too. Under FAR 13.106-2, the contracting officer evaluates on the basis set in the solicitation and has broad discretion in how. Formal evaluation plans, competitive ranges, discussions and scoring are not required, and past performance can rest on the contracting officer's own knowledge or other reasonable sources.

Late bids and late proposals are not handled the same way

Both regimes put the risk on you: your bid or proposal must reach the designated office by the time set, and if no time is set, by 4:30 p.m. local time on the due date.

A late bid under FAR 14.304(b) is considered only if it arrives before award, considering it would not unduly delay the acquisition, and either it was an electronic submission received at the initial point of entry to the Government infrastructure by 5:00 p.m. one working day before the due date, or there is acceptable evidence it reached the installation and was under Government control before the deadline.

A late proposal under FAR 15.208(b) has the same two cases plus a third: it was the only proposal received. Sealed bidding has no such exception.

Do not count on any of these. Upload a day early, keep your confirmation, and treat the deadline in the solicitation as final.

How to tell which one you hold

The package usually says it plainly, if you know where to look.

  • SF 1442, Block 2: the type of solicitation is marked sealed bid (IFB) or negotiated (RFP).
  • The cover form: SF 1442 states that if this is a sealed bid solicitation, offers will be publicly opened at the time in Block 13a.
  • The evaluation section: price and price-related factors only points to sealed bidding; a list of factors with relative importance points to an RFP.
  • The words used: bid and bidder for an IFB, proposal and offeror for an RFP, quotation for an RFQ.
  • The dollar range: simplified acquisition procedures apply at or below the simplified acquisition threshold, under FAR 13.003(a).

Frequently asked questions

Can I negotiate my price after an IFB bid opening?

No. FAR 14.101(d) says bids are evaluated without discussions, and award goes on price and price-related factors to the responsible bidder whose bid meets the invitation.

Is the lowest price always selected on an RFP?

Not under a tradeoff process. FAR 15.101-1 allows award to an offeror other than the lowest priced when the perceived benefits of a higher priced proposal merit the extra cost, as the solicitation's factors define.

Am I bound by the price in my quote on an RFQ?

FAR 13.004(a) says a quotation is not an offer and cannot be accepted to form a binding contract. A contract forms when you accept the Government's order, by writing or by performing.

Why does my small construction job say sealed bid?

FAR 36.103(a) requires sealed bidding for construction whenever the conditions of FAR 6.401(a) apply, so many construction solicitations are IFBs.

Sources and republications

The dates below concern links. They do not certify a full substantive review; claims and applicable versions still need review. Article review record.

Updated . Author: Nicolas Trendafilov, Vidikto publisher. Written with an automatic writing tool from the official texts cited. What was checked: the link of each source, opened on the day shown beside it (latest check on ).