Many federal construction jobs are bought by sealed bidding, and its rules are strict. This page follows an IFB from issue to award: the elements of the method, what makes a bid responsive, how bid opening and late bids work, what happens when you find a mistake in your price, and who gets the contract.
Not legal advice: this article explains the general rules; the solicitation of each contract governs.
Key terms
- Invitation for bids (IFB)
- The solicitation used in sealed bidding. It states the requirement fully and sets the time and place of the public bid opening.
- Responsive bid
- A bid that complies in all material respects with the invitation, as FAR 14.301 requires. A nonresponsive bid cannot be made responsive after opening.
- Responsible bidder
- A bidder the contracting officer finds able to perform under the standards of FAR subpart 9.1, before award. Responsibility concerns the firm, not the bid.
- Bid opening officer
- The official who declares the bid time has arrived, opens the bids received before it in public and has them recorded.
The five elements of sealed bidding
FAR 14.101 describes the method in five steps. The agency prepares an invitation that states its needs clearly, accurately and completely, without restrictive terms that unduly limit the number of bidders. It publicizes the invitation a sufficient time before the bid opening. Bidders submit sealed bids. The bids are evaluated without discussions. Award goes promptly to the responsible bidder whose bid conforms to the invitation and is most advantageous to the Government, considering only price and the price-related factors in the invitation.
For construction, the method is often mandatory. FAR 36.103(a) requires sealed bid procedures for construction contracts whenever the conditions of FAR 6.401(a) apply, except for work performed outside the United States and its outlying areas. That is why a small repair or paving job at a federal site so often arrives as an IFB.
What this means for you: no technical proposal, no oral presentation, no negotiation after opening. Your price and the exactness of your bid decide the outcome.
Responsiveness: comply in all material respects
FAR 14.301(a) states the core rule: to be considered for award, a bid must comply in all material respects with the invitation. The point is fairness. Every bidder prices the same requirement, so a bid that changes the terms is not comparable to the others.
The same section adds format rules. Faxed bids are not considered unless the invitation permits them. Electronic bids are considered only if the invitation specifically permits or requires that method. A bid on your own letterhead or form can be considered only if you accept all the terms of the invitation and an award would produce a binding contract on those terms.
Typical responsiveness problems are a condition added to the price, a shorter acceptance period than the invitation requires, a missing bid guarantee when one is required, or a required item left unpriced. Responsiveness is judged on the bid as opened, so it cannot be fixed afterward.
Public bid opening
Under FAR 14.402-1(a), the bid opening officer decides when the time set for opening has arrived and tells those present. The officer then personally and publicly opens all bids received before that time, reads them aloud if practical, and has them recorded. Original bids are protected until the abstract of bids is made and checked.
FAR 14.402-1(c) lets interested persons examine the bids, as long as this does not unduly interfere with Government business. In practice, the bid results show you who bid and at what price. Keep them: they tell you where your estimate stood and help you price the next job.
Late bids, modifications and withdrawals
The clause 52.214-7, dated November 1999 and placed in invitations, puts the risk on you. Your bid, modification or withdrawal must reach the Government office designated in the invitation by the exact time set. If no time is set, the deadline is 4:30 p.m. local time on the due date. FAR 14.304 states the same rules for contracting officers.
A late bid is considered only if it arrives before award, the contracting officer finds that accepting it would not unduly delay the acquisition, and one of two conditions is met. Either it was transmitted electronically and reached the initial point of entry to the Government infrastructure by 5:00 p.m. one working day before the due date, or there is acceptable evidence that it reached the installation and was under Government control before the deadline. Acceptable evidence includes the time and date stamp on the bid wrapper, other records of receipt, or statements of Government personnel.
Two other points are worth knowing. A late modification of an otherwise successful bid that makes its terms more favorable to the Government may be accepted at any time. And a bid may be withdrawn by written notice received before the deadline, or in person by the bidder or an authorized representative who proves identity and signs a receipt. Under FAR 14.304(g), late bids that are not considered stay unopened until after award, except to identify the bidder, and any bid guarantee is returned.
| Situation | Considered? | Rule |
|---|---|---|
| Electronic bid at the Government's initial point of entry by 5:00 p.m. one working day before the due date, received before award | Yes, if it does not unduly delay the acquisition | 52.214-7(b)(1), FAR 14.304(b) |
| Bid shown to be under Government control at the installation before the deadline, received before award | Yes, if it does not unduly delay the acquisition | 52.214-7(b)(1), FAR 14.304(b) |
| Late modification making an otherwise successful bid more favorable to the Government | May be accepted at any time | 52.214-7(b)(2) |
| Any other late bid | No; held unopened until after award, guarantee returned | FAR 14.304(g) |
| Deadline missed because an emergency closed the office | Deadline moves to the same time on the first work day normal processes resume | 52.214-7(d) |
Mistakes in bids
Under FAR 14.407-1, the contracting officer examines all bids for mistakes after opening. When a mistake is apparent or suspected, the contracting officer asks the bidder to verify the bid and points out the suspected error. A bid far below the others is the classic trigger.
Apparent clerical mistakes are the easy case. FAR 14.407-2 lets the contracting officer correct a mistake apparent on the face of the bid before award, after the bidder verifies the intended bid. Its examples include an obvious misplaced decimal point, obviously incorrect discounts, and an obvious mistake in the designation of unit. The correction goes into the award document; the bid itself is not changed.
Other mistakes found before award follow FAR 14.407-3, which applies only to bids that were responsive as submitted. Correction is allowed when there is clear and convincing evidence of both the mistake and the bid actually intended. If correction would put your bid ahead of lower bids, both must be ascertainable substantially from the invitation and the bid itself. When the evidence shows a mistake but not clearly the intended bid, an official above the contracting officer may let you withdraw. Each proposed determination needs the concurrence of agency legal counsel.
After award, relief is harder. FAR 14.407-4 allows rescission or reformation only on clear and convincing evidence that the mistake was mutual, or that a mistake by the contractor alone was so apparent that the contracting officer was on notice of it. A reformed price may not exceed the next lowest acceptable bid.
Award to the lowest responsible, responsive bidder
FAR 14.408-1(a) closes the process. The contracting officer awards by written or electronic notice, within the acceptance period stated in the bid or an extension, to the responsible bidder whose bid conforms to the invitation and is most advantageous considering only price and price-related factors. If fewer than three bids arrive, the contracting officer looks into why, but award is still made.
Responsiveness is about the bid; responsibility is about the bidder. FAR 14.408-2 requires the contracting officer to find the low bidder responsible under subpart 9.1 and to find the price reasonable before award, taking particular care when only one bid is received. The price analysis also considers whether a bid is materially unbalanced.
So the lowest price wins only when three things line up: the bid is responsive, the bidder is responsible, and the price is reasonable. If one fails, the award moves to the next low bid.
Your side of the process
The steps below follow an IFB from the posting to the award notice, from the bidder's chair. They assume a paper or electronic bid as the invitation allows; check the method and place stated in your invitation.
Bidding on an IFB, step by step
- Read the invitation. Note the bid opening time and place, the bid guarantee, the acceptance period and every item you must price.
- Track amendments. Check the posting for amendments until the deadline and acknowledge each one in the way the invitation states.
- Price every item. Price all required items without adding any condition, since a qualified bid can be rejected as nonresponsive.
- Deliver early. Submit by a method the invitation authorizes, well before the time set, and keep proof of delivery.
- Attend or read the opening. Note the bid results read at the public opening, or ask for the abstract afterward.
- Answer verification requests. If asked to verify your bid, check your estimate at once and answer in writing with your worksheets.
- Prepare for award. Have responsibility information and bonds ready so that award can follow within the acceptance period.
Frequently asked questions
Can I talk to the contracting officer about my price after bid opening?
No negotiation takes place. FAR 14.101 says bids are evaluated without discussions. The only exchange about your price is a verification request if the contracting officer suspects a mistake.
My bid was delivered on time to the mailroom but reached the office late. Does it count?
It may. Under 52.214-7, a late bid can be considered if it arrives before award, does not unduly delay the acquisition, and acceptable evidence shows it was under Government control at the installation before the deadline. A time and date stamp on the wrapper is one form of evidence.
I left out a cost in my bid. Can I raise my price?
Only under FAR 14.407-3, with clear and convincing evidence of the mistake and of the bid you intended. If the corrected bid would move ahead of lower bids, both must be ascertainable substantially from the invitation and the bid itself. Otherwise you may be allowed to withdraw, or neither correction nor withdrawal may be allowed.
Does the lowest bid always win?
The lowest bid wins only if it is responsive, the bidder is responsible and the price is reasonable, under FAR 14.408-1 and 14.408-2. If any of these fails, the contracting officer moves to the next low bid.
Sources and republications
The dates below concern links. They do not certify a full substantive review; claims and applicable versions still need review. Article review record.
- FAR 14.101, Elements of sealed bidding, link checked on
- FAR 36.103, Methods of contracting, link checked on
- FAR 14.301, Responsiveness of bids, link checked on
- FAR 14.304, Submission, modification, and withdrawal of bids, link checked on
- FAR 52.214-7, Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999), link checked on
- FAR 14.402-1, Unclassified bids (opening of bids), link checked on
- FAR 14.407-1, Mistakes in bids, General, link checked on
- FAR 14.407-2, Apparent clerical mistakes, link checked on
- FAR 14.407-3, Other mistakes disclosed before award, link checked on
- FAR 14.407-4, Mistakes after award, link checked on
- FAR 14.408-1, Award, General, link checked on
- FAR 14.408-2, Responsible bidder, reasonableness of price, link checked on